Contact
Sequence

Baselines & variance

Capturing a baseline, the three rules that make one worth arguing from, the variance columns, and why a row outside a partial baseline reports as unbaselined rather than on plan.

A baseline is what you said you would do. It is the one place in Sequence where a derived value is deliberately frozen and stored rather than recomputed — everywhere else a stored derived value is a bug, and here it is the entire point. "What did we say we would do" cannot be recomputed from today's inputs.

Three rules#

1. Immutable once taken. Re-baselining creates a new baseline; the old one is never overwritten. A baseline is what a delay claim is argued against, so a baseline that can be edited is worth nothing in the argument.

2. Named, timestamped and attributed. "Baseline" tells you nothing six months on. Rev C — approved 2026-03-14 does. The name is required and the capture records who took it and when.

3. A partial baseline records what it covered. Baselining a selection is legitimate. Rows outside it report as unbaselined, never as zero variance — zero variance means "on plan", no baseline means "we never said", and conflating them is how a schedule reports itself healthy for work nobody ever planned.

What is captured#

Per row: start, finish, duration in working days as the engine computed it at capture, and cost.

⚠ Baseline cost is nullable, and null is not zero. A baseline taken before the schedule was priced captured no cost. Storing zero would make planned value read "this work was planned to cost nothing", which reports a variance of the entire budget rather than an absent baseline. Baselines captured before costing existed load as uncosted rather than as free.

Variance#

Every baselined row reports one of four states:

StateMeaning
On planWithin tolerance of the baseline
LateFinishing after the baseline finish
EarlyFinishing before it
UnbaselinedThis row was not in the baseline

The baseline columns — baseline start, baseline finish, baseline duration, baseline cost, and the variances against each — are available in the grid, in filters and in conditional formatting rules, so "colour everything more than five days late" is a rule rather than a report.

Where else a baseline is used#

  • Quality checks points 11 and 14 both need one, and report not-applicable without it.
  • Alerts include a baseline-slip rule.
  • Earned value takes its budget from the baselined cost.